Arizona Mechanics Lien Guide

Everything you need to know about filing a mechanics lien in Arizona — deadlines, requirements, costs, and a free document generator.

Understanding Arizona Mechanics Lien Law

Arizona mechanics lien rights are governed by Ariz. Rev. Stat. §§ 33-981 to 33-1008, § 33-992.01. To file a mechanics lien in Arizona, you must record your claim with the County Recorder's Office in the county where the property is located. The estimated recording fee is $25-$40, though fees vary by county.

Some claimant types in Arizona are required to send a preliminary notice before filing a lien. Check the requirements for your specific role below.

Arizona Mechanics Lien Deadlines by Role

RolePreliminary NoticeLien Filing Deadline
General Contractor20 days from first furnishing120 days from completion
Subcontractor20 days from first furnishing120 days from completion
Material Supplier20 days from first furnishing120 days from completion

Use our deadline calculator to find your exact filing dates based on your project timeline.

Requirements by Role

General Contractor

Lien Deadline
120 days from completion
Preliminary Notice
Required — 20 days from first furnishing
Filing Office
County Recorder's Office
Estimated Recording Fee
$25-$40
Statute Reference
Ariz. Rev. Stat. §§ 33-981 to 33-1008, § 33-992.01

All parties must send a 20-day preliminary notice. GCs must file within 120 days of completion (60 days if Notice of Completion recorded).

Subcontractor

Lien Deadline
120 days from completion
Preliminary Notice
Required — 20 days from first furnishing
Filing Office
County Recorder's Office
Estimated Recording Fee
$25-$40
Statute Reference
Ariz. Rev. Stat. §§ 33-981 to 33-1008, § 33-992.01

Must send 20-day preliminary notice from first furnishing. File within 120 days of completion (60 days if NOC).

Material Supplier

Lien Deadline
120 days from completion
Preliminary Notice
Required — 20 days from first furnishing
Filing Office
County Recorder's Office
Estimated Recording Fee
$25-$40
Statute Reference
Ariz. Rev. Stat. §§ 33-981 to 33-1008, § 33-992.01

Must send 20-day preliminary notice. File within 120 days of completion (60 days if NOC recorded).

What You Need to File

Gather the following information before preparing your Arizona mechanics lien document:

  • ✓Your full legal name (or business name)
  • ✓Property owner's name
  • ✓Property address (legal description preferred)
  • ✓Description of work performed or materials supplied
  • ✓Total amount owed
  • ✓Name of the party who hired you

How to File a Mechanics Lien in Arizona

  1. 1

    Send Your Preliminary Notice

    Check whether your role requires a preliminary notice in Arizona. If required, send it within the specified deadline to preserve your lien rights. Learn more in our preliminary notice guide.

  2. 2

    Gather Your Documentation

    Collect all required information including contract details, payment records, and property information. See the checklist above for the complete list.

  3. 3

    Prepare Your Lien Document

    Use our free Arizona lien generator to create a state-compliant mechanics lien document with all required fields.

  4. 4

    Record with the County Recorder's Office

    File your completed lien document with the County Recorder's Office in the county where the property is located. Expect to pay approximately $25-$40 in recording fees.

  5. 5

    Serve Notice on the Property Owner

    After recording, serve a copy of the filed lien on the property owner as required by Arizona law. Keep proof of service for your records.

Important Notes for Arizona

All parties must send a 20-day preliminary notice. GCs must file within 120 days of completion (60 days if Notice of Completion recorded).

Must send 20-day preliminary notice from first furnishing. File within 120 days of completion (60 days if NOC).

Must send 20-day preliminary notice. File within 120 days of completion (60 days if NOC recorded).

Frequently Asked Questions

How long do I have to file a mechanics lien in Arizona?

Deadlines vary by role. General Contractors have 120 days from completion. Subcontractors have 120 days from completion. Material Suppliers have 120 days from completion. These deadlines are strictly enforced — missing them means losing your lien rights.

Do I need to send a preliminary notice in Arizona?

General Contractors must send a preliminary notice within 20 days of first furnishing. Subcontractors must send a preliminary notice within 20 days of first furnishing. Material Suppliers must send a preliminary notice within 20 days of first furnishing. Even when not required, sending a preliminary notice is recommended as a best practice.

Where do I file a mechanics lien in Arizona?

In Arizona, mechanics liens are filed with the County Recorder's Office in the county where the property is located.

How much does it cost to file a mechanics lien in Arizona?

The estimated recording fee in Arizona is $25-$40. Fees vary by county and may change. Contact your local County Recorder's Office for current rates.

What information do I need to file a mechanics lien in Arizona?

You will need: Your full legal name (or business name), Property owner's name, Property address (legal description preferred), Description of work performed or materials supplied, Total amount owed, Name of the party who hired you. Subcontractors and suppliers may also need the name of the party who hired them.

Related Resources

Ready to File Your Arizona Mechanics Lien?

Our guided form will walk you through the state-specific requirements and generate your document.

Generate Your Arizona Lien Document

Disclaimer: This guide provides general information about Arizona mechanics lien law and is not legal advice. Laws change frequently and may vary based on project type, contract terms, and local requirements. Always consult with a licensed attorney for advice specific to your situation.