Wyoming Mechanics Lien Guide
Everything you need to know about filing a mechanics lien in Wyoming — deadlines, requirements, costs, and a free document generator.
Understanding Wyoming Mechanics Lien Law
Wyoming mechanics lien rights are governed by Wyo. Stat. §§ 29-1-201 to 29-2-110. To file a mechanics lien in Wyoming, you must record your claim with the County Clerk's Office in the county where the property is located. The estimated recording fee is $15-$30, though fees vary by county.
Some claimant types in Wyoming are required to send a preliminary notice before filing a lien. Check the requirements for your specific role below. Additionally, Wyoming requires a Notice of Intent to Lien before filing.
Wyoming Mechanics Lien Deadlines by Role
| Role | Preliminary Notice | Lien Filing Deadline | Notice of Intent |
|---|---|---|---|
| General Contractor | 30 days from first furnishing | 150 days from last furnishing | 20 days before filing |
| Subcontractor | 30 days from first furnishing | 120 days from last furnishing | 20 days before filing |
Use our deadline calculator to find your exact filing dates based on your project timeline.
Requirements by Role
General Contractor
- Lien Deadline
- 150 days from last furnishing
- Preliminary Notice
- Required — 30 days from first furnishing
- Notice of Intent
- Required — 20 days before filing
- Filing Office
- County Clerk's Office
- Estimated Recording Fee
- $15-$30
- Statute Reference
- Wyo. Stat. §§ 29-1-201 to 29-2-110
GCs must file within 150 days. Must give notice before receiving any payment. Must serve 20-day Notice of Intent before filing. Serve owner by certified mail within 30 days.
Subcontractor
- Lien Deadline
- 120 days from last furnishing
- Preliminary Notice
- Required — 30 days from first furnishing
- Notice of Intent
- Required — 20 days before filing
- Filing Office
- County Clerk's Office
- Estimated Recording Fee
- $15-$30
- Statute Reference
- Wyo. Stat. §§ 29-1-201 to 29-2-110
Must file within 120 days. Must give notice to owner within 30 days of first furnishing. Must serve 20-day Notice of Intent before filing. Serve owner by certified mail.
What You Need to File
Gather the following information before preparing your Wyoming mechanics lien document:
- ✓Your full legal name (or business name)
- ✓Property owner's name
- ✓Property address (legal description preferred)
- ✓Description of work performed or materials supplied
- ✓Total amount owed
- ✓Name of the party who hired you
How to File a Mechanics Lien in Wyoming
- 1
Send Your Preliminary Notice
Check whether your role requires a preliminary notice in Wyoming. If required, send it within the specified deadline to preserve your lien rights. Learn more in our preliminary notice guide.
- 2
Send a Notice of Intent to Lien
Wyoming requires you to notify the property owner of your intent to file a lien before recording it. This gives them a final chance to resolve the payment dispute.
- 3
Gather Your Documentation
Collect all required information including contract details, payment records, and property information. See the checklist above for the complete list.
- 4
Prepare Your Lien Document
Use our free Wyoming lien generator to create a state-compliant mechanics lien document with all required fields.
- 5
Record with the County Clerk's Office
File your completed lien document with the County Clerk's Office in the county where the property is located. Expect to pay approximately $15-$30 in recording fees.
- 6
Serve Notice on the Property Owner
After recording, serve a copy of the filed lien on the property owner as required by Wyoming law. Keep proof of service for your records.
Important Notes for Wyoming
GCs must file within 150 days. Must give notice before receiving any payment. Must serve 20-day Notice of Intent before filing. Serve owner by certified mail within 30 days.
Must file within 120 days. Must give notice to owner within 30 days of first furnishing. Must serve 20-day Notice of Intent before filing. Serve owner by certified mail.
Frequently Asked Questions
How long do I have to file a mechanics lien in Wyoming?
Deadlines vary by role. General Contractors have 150 days from last furnishing. Subcontractors have 120 days from last furnishing. These deadlines are strictly enforced — missing them means losing your lien rights.
Do I need to send a preliminary notice in Wyoming?
General Contractors must send a preliminary notice within 30 days of first furnishing. Subcontractors must send a preliminary notice within 30 days of first furnishing. Even when not required, sending a preliminary notice is recommended as a best practice.
Where do I file a mechanics lien in Wyoming?
In Wyoming, mechanics liens are filed with the County Clerk's Office in the county where the property is located.
How much does it cost to file a mechanics lien in Wyoming?
The estimated recording fee in Wyoming is $15-$30. Fees vary by county and may change. Contact your local County Clerk's Office for current rates.
What information do I need to file a mechanics lien in Wyoming?
You will need: Your full legal name (or business name), Property owner's name, Property address (legal description preferred), Description of work performed or materials supplied, Total amount owed, Name of the party who hired you. Subcontractors and suppliers may also need the name of the party who hired them.
Do I need to send a Notice of Intent to Lien in Wyoming?
Yes. General Contractors must send a Notice of Intent at least 20 days before filing. Subcontractors must send a Notice of Intent at least 20 days before filing. This notice gives the property owner a final opportunity to resolve the payment dispute before a lien is filed.
Related Resources
What Is a Mechanics Lien?
A comprehensive overview of mechanics liens and how they protect your right to payment.
How to File a Mechanics Lien
Step-by-step guide to preparing and filing your mechanics lien document.
Preliminary Notice Requirements
Learn when and how to send a preliminary notice to protect your lien rights.
Deadline Calculator
Calculate your exact filing deadlines based on your project dates and role.
Ready to File Your Wyoming Mechanics Lien?
Our guided form will walk you through the state-specific requirements and generate your document.
Generate Your Wyoming Lien DocumentDisclaimer: This guide provides general information about Wyoming mechanics lien law and is not legal advice. Laws change frequently and may vary based on project type, contract terms, and local requirements. Always consult with a licensed attorney for advice specific to your situation.